Skip to content

General Scope of Work for Construction Contracts

Table of Contents Section Title Page

Purpose2
Scope2
Related Documents2
Definitions3
Order of Precedence of Contract Documents3
Contract and Scope Changes4
General4
Schedule5
Safety, Quality and Industrial Relations7
Permits and Regulations10
Applicable Codes10
Communications, Correspondence, and Drawing Submittals11
Field Reporting12
Materials and Substitutions13
Workmanship13
Superintendents14
Equipment and Tools15
Layout of Work and Site Conditions15
Temporary Facilities16
Housekeeping16
Receiving Purchaser-Supplied Materials17
Protection of Materials and Work18
Testing19
Acceptance of Work21
Clearing the Site21
Change Log21
Purchaser’s Site Office Requirements22

1. purpose

1.1 This fabrication and erection specification defines the general scope of work requirements for construction contracts and the scope for the contractor that is not covered in other specifications.

2. scope

2.1 This specification applies to all erection contracts. In some instances, specific examples or requirements are specified that relate to a particular discipline; these shall be applied appropriately to other disciplines.

2.2 This specification shall be applied in conjunction with the project-specific scope of work documents and the appropriate engineering standards referred to in the contract package transmittal. The project-specific specifications, drawings, and documents might supersede some parts of this general scope of work specification for that particular project.

2.3 The project-specific scope of work documents and project specifications have precedence over this general scope of work specification. No exceptions shall be permitted without the written approval of the purchaser.

3. RELATED DOCUMENTS

3.1 Purchaser Engineering Documents – Air Products in America 3PI70001 Cleaning Levels and Acceptance Criteria for Air Separation Plant Piping and Equipment 4AEL-620300 Electrical Work 4WCE-600500 Crane and Lifting Procedures 4WCE-600700 Construction Safety 4WCE-670200 Fabrication and Erection of Process Piping 4WPI-EW44001 Pressure Testing of Process Piping and Equipment 600.002 General Project Data (Project Specific) 600.600 Drawing Requirements (Project Specific)

3.2 Purchaser Engineering Documents – Air Products in Europe 3PI70001 Cleaning Levels and Acceptance Criteria for Air Separation Plant Piping and Equipment 4WCE-600500 Crane and Lifting Procedures 4WCE-600510 Erection of Cold Boxes 4WCE-600700 Construction Safety 4WPI-EW44001 Pressure Testing of Process Piping and Equipment 4WPI-SW70006 Cleaning of Piping and Inline Equipment 4ECE-M20 Instrument Installation

3.3 American Society for Testing and Materials A 105 Specification for Forgings, Carbon Steel, for Piping Components

3.4 The American Society of Mechanical Engineers (ASME) B16.5 Pipe Flanges and Flanged Fittings

3.5 European Committee for Standardization (CEN) EN10204 Metallic Products – Types of Inspection Documents  

3.6 European Economic Community (EEC) 97/23/EC  European Pressure Equipment Directives (PED) – effective 29 May 2002

3.7 International Organization for Standardization (ISO) ISO 9000 Quality management and quality assurance standards

Note: The latest edition of each document listed in Section 3 at the date of the contract shall be used.

4. DEFINITIONS

4.1 Purchaser representative shall mean the designated representative of Purchaser in charge of the work at the site or elsewhere.

4.2 Approval by Purchaser shall mean approval in writing unless otherwise specified.

4.3 Contract documents shall mean the purchase order and/or construction contract form, Award Letter/Notice, bulletins, addenda, general conditions, and all drawings, specifications, and documents referenced therein or delivered to the contractor thereunder, including (but not limited to) these general specifications.

4.4 Contractor shall mean the company and its subcontractors awarded the work by Purchaser and named in the construction agreement.

4.5 Equal shall mean equal as approved in writing by Purchaser or the Purchaser representative.

4.6 General conditions shall mean the “General Conditions for Construction Agreements” or “General Conditions of Contract” included as part of the contract documents.

4.7 Owner shall mean the Purchaser Company or Client nominated in the purchase order unless specifically identified otherwise in the construction agreement and contract documents.

4.8 urchaser shall mean the Purchaser, Joint Venture, Project Company, or Client Company placing the purchase order on the contractor. Work shall mean the labor, services, materials, and equipment as contracted.

5. ORDER OF PRECEDENCE OF CONTRACT DOCUMENTS

5.1 When a direct conflict exists among the contract documents, the contractor shall immediately contact Purchaser for clarification.

5.2 The following order of precedence of contract documents shall apply, unless otherwise specified in the purchase order itself:

5.2.1 Contract amendments and addenda issued subsequent to contract award, including associated latest revisions/additions to the contract drawings.

5.2.2 Purchase Order or Construction Contract Form.

5.2.3 Award Letter/Notice.

5.2.4 Conditions for Construction Agreement.

5.2.5 Bulletins issued before contract award, including the latest revisions/additions to the contract drawings associated with each.

5.2.6 600.002 of these specifications or project specific scope of work.

5.2.7 600.600 of these specifications and contract drawings and documents included or referenced therein or Contract drawing register.

5.2.8 Construction Specification 4WCE-600001 (this specification).

5.2.9 Other construction specifications (for example, 4WCE-670200, 4AEL-620300, or 4WPI-EW44001).

5.2.10 Engineering standards, design standards, and standard drawings.

6. CONTRACT AND SCOPE CHANGES

6.1 Changes to the original scope of work may only be made by one of the following: Bulletins issued in numerical order before award. Addenda issued in numerical order after award. Construction Change Orders (CCOs) issued in numerical order after the contractor is on-site [referred to as Construction Change Requests in Europe (CCRs)].

6.2 The contractor is not authorized to proceed with any work beyond the original scope of the contract without written authorization by the Purchaser representative.

7. GENERAL

7.1 The purchaser sets high goals in safety and quality, and all work performed according to this specification shall comply with safe and quality-conscious practices.

7.2 For the complete responsibilities of the contractor under the purchase order contract, all relevant drawings, specifications, and associated documents as listed in the purchase order contract shall be read in conjunction with this document (for example, 4WCE-670200 for piping erection). The contractor shall undertake all work according to the contract drawings, drawing notes, standards, and specifications referenced herein. The contractor shall only employ personnel trained and competent in the work they are being asked to do. Equipment and plant shall be serviceable and shall be inspected with suitable certification. The contractor’s employees shall at all times use best trade practices in the work being performed.

7.3 The contractor shall be aware that the intent is for the scope to be fully inclusive of all activities necessary to complete the erection of the facility from receipt of equipment to handover ready for commissioning. Where the contract is awarded on a bills of quantity basis, the contractor, as an experienced contractor, shall ensure that their offer is fully inclusive and the contractor shall identify any activities they consider omitted from the bills of quantity activity listing and include the price for these accordingly in an appropriate rate within the bills of quantity. The scope of work, any bill of quantity, and drawings/specifications shall be viewed as a whole so that the contractor shall ensure that all scope/work identified, even if not identified as an explicit item in the bill, is priced within the general rates.

7.4 The contractor shall procure all gases for use at site, whether required in bulk form or cylinders, from Air Products or Air Products subsidiaries. This condition is subject to such gases being made available by Purchaser as and when required at no premium over local rates from other sources.

7.5 The contractor shall ensure that they make the best use of the free issue material provided. Adequate material has been provided for cutting allowances. For Monel materials or other exotic materials, no spare fittings will be provided and absolutely the minimum excess piping will have been provided. Under special conditions the Purchaser will provide extra material for welding qualification if requested by the contractor. The contractor will replace any equipment, materials, pipe, or fittings damaged or lost by the contractor. Within four weeks of receiving the final drawings and materials lists, the contractor shall confirm that sufficient material is being provided.

7.6 The contractor will be required to work alongside other contractors and often where there is limited space. Coordination between contractors shall be their own responsibility on a day‑to‑day basis. The Purchaser relies on the contractor to ensure that adequate communication occurs. The Purchaser will only adjudicate when contractors have discussed issues and are unable to resolve a conflict. The Purchaser shall not be liable for any failure by any contractor to adequately coordinate their work.

8. SCHEDULE

8.1 For this contract, time is of the essence. Failure of the contractor to complete the work within the scheduled completion and interim milestone dates specified in the contract documents shall constitute grounds for default of this contract.

8.2 The contractor shall furnish an outline bar chart schedule with the contractor’s bid according to the key date schedule and any specific form included with the bid documents. The contractor’s schedule shall be activity based, if specified, using any breakdown provided in the tender/bid documentation. It shall clearly indicate weekly manpower loading for direct, indirect, and subcontract labor and the scheduled start and completion dates for each item.

8.3 For the execution of the contract, the contractor shall generally develop a critical path network (CPN) for the project. In the United States within two weeks after contract award, Purchaser themselves, with the assistance of the contractor, will prepare a detailed construction schedule (based on the contract and pre-award agreements) to be issued to the contractor for review. Interim, milestone, completion, and commissioning dates detailed in 600.002 will be used as the basis for development of this schedule.

8.4 When not done by the Purchaser, the contractor’s schedule shall be at an activity-based level of planning with a suitable method of progress measurement agreed with the Purchaser representative. The following paragraphs outline the expected method of planning a mechanical-based contract; however for other disciplines, a suitable equivalent shall be used (for example, numbers of terminations, loops, cables pulled, concrete poured). For a mechanical-based contract, this should indicate the interfaces between prefabrication, blast and prime painting, erect, weld‑out, support, punch-out, and test. The activities shall be resource loaded with durations to enable the production of a resource requirement histogram. After resolution of any necessary changes and final agreements, the contractor shall sign the original copy of the schedule. This signed and agreed-to contract schedule shall be binding with all requirements of the contract documents.

8.5 The contractor’s bid shall be based on the industry standard working week at the jobsite location, and shall comply with local labor laws. When not specified or controlled the preferred workweek is 40 hours ordinary time, preferably consisting of five 8-hour days. An alternate work schedule may be proposed for Purchaser acceptance provided that the contractor will furnish the labour, equipment, supervision, and other services required.

8.6When the contractor’s bid is based on the use of premium time to meet the schedule requirements specified in the project-specific key date summary, the bid must be specific as to where, when, and how much premium time is required and the incremental costs involved. Excessive overtime has proven to decrease safety awareness and increase incidents and to reduce efficiency. The normal scheduled workweek shall not exceed 60 hours or six days per week without approval from Purchaser management. Short unscheduled overtime will be left to the Purchaser representative’s discretion and approval.

8.7 All schedules must allow for inclement weather at the job site locale that might cause work delays or stoppages during the specific time of the year that the work is to be performed. No extensions to schedules will be granted by Purchaser unless unusually abnormal weather occurs and can be documented as such to Purchaser satisfaction. The contractor shall, therefore, include in the contractor’s bid, when appropriate, sufficient provision for accommodations (such as temporary shelter, heaters) that may be required to successfully complete the work in cold, wet, or inclement weather.

8.8 The contractor shall furnish sufficient workforce, supervision, and equipment and shall work such hours (including overtime, weekends, and holidays) as might be necessary to ensure completion of the work, as well as any established interim milestones following the agreed-to contract schedule.

8.9 Progress will be closely monitored regarding the contract schedule and if it becomes evident to Purchaser that the actual progress of the contractor is not in compliance with the contract schedule because of slow progress, delays in securing materials, insufficient or unqualified labor, incompetent supervision, negligence, or any other such cause within the contractor’s control, the contractor shall take prompt and adequate action to bring the work in compliance with the schedule and eliminate any interference with the progress of other contractors or production schedules. The contractor shall not be entitled to any additional compensation for additional labor, equipment, materials, overtime, or other methods that are required to maintain the agreed-to schedule.

8.10 The General Conditions assume that the contractor will be expected to perform extra work beyond the base contract work and within the original contract schedule. The provisions are detailed in the general and project-specific Terms and Conditions.

8.11 Failure by the contractor to comply with the requirements of these paragraphs resulting in additional costs incurred by Purchaser or other contractors (whose work is dependent on the successful completion of work by this contractor according to the agreed-to contract schedules) shall constitute grounds for backcharge to the contractor for these costs.

8.12 Fabrication Control and Reporting

8.12.1 The contractor shall develop a proposed fabrication sequence on a spool-by-spool basis, which shall be used to develop progress S-curves for spool fabrication. The contractor shall also determine the total numbers of spools to be prefabricated and quantity of welds.

8.12.2 The contractor shall report weekly on fabrication progress on both tabular and S-curve formats, split for each material type and summarized overall for the week period.

8.12.3 The report shall list the number of spools complete for the weekly period and cumulatively, the quantity of welds complete, and the percentage progress. All these shall be measured against planned progress.

8.12.4 The contractor shall also provide a similar report for blast and prime painting of spools based on the number of spools complete, and the contractor shall maintain a marked-up bar chart to be reviewed weekly, showing the progress of each spool through the fabrication process, including buildability status.

8.13 Site Erection Control and Reporting

8.13.1 The contractor shall develop a detailed erection plan based on the CPN that shall detail the installation of all materials, including installation of equipment, build-up of compressors, erection of piping, weld-out, support, punch-out, and testing to handover. When planning the work, contractor shall take into account the presence of other contractors who may be working on site at the same time. Purchaser cannot guarantee contractor free, uninterrupted access to work areas.

8.13.2 This plan shall be in bar chart form and shall be mounted on the conference room wall and marked up on a daily basis; a string cursor shall indicate “time now.” The progress against this plan will be reviewed in the formal weekly progress meeting.

8.13.3 The contractor shall develop and implement an effective method of allocating work to his field supervisors and of accurately monitoring progress.

8.13.4 From four weeks before the handover of the first systems, planning reports shall be available based on test packs/systems.

8.13.5 The contractor shall cooperate to the fullest extent with Purchaser, Purchaser customers, and other contractors and shall not be granted schedule extensions or additional compensation for any effect on contractor performance caused by other contractors executing their normal work in the same areas simultaneously.

8.13.6 Any overtime required for other reasons at the request of Purchaser will be authorized by issuing of a CCO. Only the premium portion of the overtime will be compensated to the contractor by Purchaser. It is the contractor’s responsibility to ensure that he obtains Purchaser approval for these CCOs and that timesheets are signed by Purchaser representative.

8.14 Phased Handovers

8.14.1 The contractor’s execution strategy shall allow for the phased start-up of the plant, which means that various process systems will need to be handed over in advance of overall mechanical completion. These handovers will form key milestones in the contract execution.

8.14.2 Accordingly, the contractor’s planning system shall be able to report on both “by area” and “by system” basis. The contractor shall also ensure that their field execution strategy will also enable this change of emphasis during the construction period.

9. SAFETY, QUALITY AND INDUSTRIAL RELATIONS

9.1 Safety

9.1.1 Construction safety procedures as specified in the project specific scope of work, 4WCE-600700, and any other site-specific safety related documents will be strictly enforced.

9.1.2 The Purchaser representative shall have the final decision relating to all safety issues. The decision of the Purchaser representative shall be binding on the contractor and contractor’s subcontractor(s).

9.1.3 The contractor shall submit copies of all insurance certificates to the Purchaser representative before the start of any work according to the requirements specified in the general conditions or contract documents. Purchaser should be named as “Additional Insured.” The contractor shall provide an updated insurance certificate upon renewal if a certificate expires during the course of this contract.

9.1.4 The contractor shall be responsible for their subcontractors. All contract requirements shall apply to subcontractors. The contractor agrees to abide by Purchaser safety qualification criteria, which require an experience modification rate (EMR) of less than or equal to 0.90 (U.S. only), OSHA Recordable Incident Rate of less than or equal to 6.0, and Lost Work Day Case (CWDAs) rate of less than or equal to 3.0.

9.1.5 The contractor shall submit in writing for approval verification of subcontractors’ compliance to these rates to Purchaser with the bid proposal. After award if the contractor wishes to propose a subcontractor different than proposed in bid documents, they must submit the past three years of safety statistics for this subcontractor for approval by Purchaser. If there are unusual circumstances, the contractor may petition Purchaser for a variance. Approval of this variance will be solely at Purchaser discretion.

9.2 Health and Safety Plan

9.2.1 The contractor shall supply an outline plan at tender/bid and a detailed health and safety plan before work begins. This shall be based on the requirements detailed in the Purchaser or Client’s overall health and safety plan.

9.2.2 This document shall include as a minimum: A clear statement of the contractor’s policy regarding health and safety. A description of how this policy is administered. The level, frequency, and means of education and training on health and safety matters. An organizational breakdown showing who is responsible for health and safety on site. An action plan showing how the safe execution of the work is to be ensured. A letter from the senior management and from the site management team confirming their personal commitment to safety on the site. A typical format is available from the Purchaser. Details of the provision and maintenance of safety equipment and instruction and training in its use.

9.2.3 The contractor will be required to provide facilities (such as video or training room) to undertake site safety inductions for all its personnel, subcontractors, and for other Purchaser contractor personnel as shall be necessary. In addition, the contractor shall allow for periodic safety training, central addresses, or meetings of all their site personnel as requested by the Purchaser representative.

9.2.4 The contractor will be required to work under a permit to work system at certain times and for certain activities specified by the purchaser. The contractor might be required to train or have trained personnel in the use of the permit to work procedure.

9.3 Quality Assurance and Fabrication Records

9.3.1 Before starting any site work, the Purchaser site representative will hold a meeting to review contract specifications, drawings, inspection requirements and QA/QC documentation required. This meeting is different than, and will be held separate from, the safety meeting referenced in other contract documents.

9.3.2 If required by contract documents, the contractor shall provide a detailed quality plan according to ISO 9000 or equivalent that shall be approved by the Purchaser. The quality plan shall detail procedures, documentation, inspection, and control systems that shall be implemented by the contractor to ensure that the requirements stated in the contract documents are met. The Purchaser reserves the right to audit the contractor at any stage in order to verify that the quality assurance procedures have been effectively implemented.

9.3.3 The quality plan shall be submitted to the Purchaser at least four weeks before any prefabrication or erection work begins. Throughout the duration of the contract, the contractor shall progressively compile quality assurance dossiers. The master dossier shall contain the original documents endorsed where necessary by the approval authority or copies authenticated by an approval authority, together with material certificates for material supplied by the contractor or free issued by the Purchaser. These documents are to be submitted in an electronic format compiled on a CD/DVD to the purchaser.

9.3.4 The standard of cleanliness of equipment and piping systems in a cryogenic plant is of the highest operating and safety importance. The contractor shall ensure they fully understand these requirements and know how to achieve them. General guidance is provided in 3PI70001. The contractor should note that cleaning of the piping systems by circulation cleaning after installation of the process piping is not allowed for a cryogenic plant. Piping shall be cleaned before installation and the installed lines shall be kept clean and purged.

9.3.5 For critical systems (for example, oxygen), the Purchaser reserves the right to undertake whatever inspections of cleanliness of equipment, piping, and other components are necessary to be satisfied that the contractor is consistently achieving the required standard of cleanliness.

9.3.6 The contractor shall be fully responsible for meeting all third party inspection requirements specified. In Europe this shall include approvals and inspections required by a notified body under the PED. This shall include arranging for all necessary inspections and witnessed tests and collating authenticated records such that the final dossiers can be submitted to the Purchaser for onward transmittal to the client for approval. The cost of all third party inspection approvals and site inspections shall be paid by the contractor. The contractor shall be responsible for arranging and scheduling all such inspection and approvals.

9.3.7 The contractor shall propose their preferred notified body and third party inspection organization within their bid. The quality assurance dossiers shall contain documents as detailed in the specific discipline specifications (for example, 4ECE-M20 for instrument installation). For mechanical work that is not detailed in a separate specification, the contents shall include, but shall not be limited to, all of the following documents which shall be clearly identified and indexed:

9.3.8 For the piping systems and process equipment erection: Quality procedures. Non-destructive testing (NDT) inspection procedures. NDT inspector personal qualifications and certificates, including annual eye examine results. Welding procedure specifications and procedure qualification certificates. Welder competence certificate with dates of requalification. Welders log identifying the procedures each welder is qualified to perform. Material test certificates. Weld electrode and filler material certificates. Nondestructive testing reports for radiography, dye penetrant, and magnetic particle examination. Inspection reports, nonconformance reports, repair, and rectification reports. Marked-up isometric drawings, weld procedure specification and radiography. Identification, number for welds, and when specified in the project-specific scope of work, material certificate numbers against each item. Welder records to identify each welder against individual welds. Pressure test certificates. Test gauge calibration certificates. Cleanliness check certificates. Painting quality control records. Insulation quality control records. Final inspection report. Copies of release notes. As-built isometric drawings. Signed-off punchlists. Signed-off equipment installation protocols. Certificate of conformity from the nominated Notified Body (for PED work only).

9.4 Industrial Relations

9.4.1 The contractor shall provide in their tender/bid proposals for the management of industrial relations for the duration of the contract. These proposals shall list as a minimum any labor agreement that they propose to use, the trade unions involved, the normal working hours available, the overtime hours permitted, weekend working permitted, shift pattern permitted, arrangements for both annual holidays and dates of fixed holidays, and details of any productivity bonus schemes.

9.4.2 During the duration of the contract, if the contractor is involved in any trade dispute, the contractor shall inform the Purchaser representative of the existence of the dispute, the reason for the dispute, and the arrangements being made to resolve it. This information shall take the form of an immediate initial oral report followed by written confirmation.

9.4.3 The contractor shall provide details with their tender/bid proposals of how they will manage the provision of labor to execute the works. These proposals shall list sources of labor and state the proportion that are full-time employees of the contractor. The contractor shall detail methods of trade testing to verify skill levels and if necessary the method of organizing visas and travel.

9.4.4 All labor conditions shall be fully compliant with national requirements.

10. PERMITS AND REGULATIONS

10.1 In the U.S., the contractor shall secure and pay for any and all building licenses, plan reviews, and permits regarding the work unless otherwise stated in Project Specific Scope of Work of the contract specifications. Purchaser will provide the engineering drawings necessary to obtain the permit.

10.2 The contractor shall comply with and obtain at the contractor’s own expense all requisite contractor registration licenses and permits and any licenses or permits required by National, U.S. federal, state, or local laws and ordinances, regulating authorities, commissions, or other authorities as might be necessary under the law in the territory in which the work is being performed.

10.3 If the contractor becomes aware of any violation of any ordinance, law, or code, the contractor shall immediately inform the Purchaser representative in writing.

10.4 The contractor shall schedule and pay for any inspections that might be required to comply with National, U.S. federal, state, or local regulatory agencies and authorities and shall present final approval copies of all permits, licenses, and documents to the Purchaser representative.

11. APPLICABLE CODES

11.1 All material and workmanship shall comply and conform with the latest versions and amendments of all applicable codes specified in the contract documents, as well as any applicable National, federal, state, and local codes, ordinances, and regulations. Contractor shall have reasonable access to those codes necessary to appropriately support their scope of work.

12. COMMUNICATIONS, CORRESPONDENCE, AND DRAWING SUBMITTALS

12.1 Before Award

12.1.1 All formal correspondence before award of the contract shall be directed to the Procurement Department in the Purchasers Head Office,

12.1.2 All questions concerning commercial documents shall be directed to the Purchaser Procurement Department buyer or designee.

12.1.3 All technical questions shall be directed to the Purchaser Construction Engineering Manager (or designee) or to the Purchaser Project Engineering Manager (or designee).

12.1.4 All correspondence shall include the Purchaser inquiry number, Purchaser project name and number, and related subject as applicable.

12.2 After Award

12.2.1 All formal correspondence and questions after the award of the contract shall be directed to the Purchaser representative at the job site unless otherwise advised.

12.2.2 All correspondence shall include the Purchaser purchase order/contract number, Purchaser project name and number, job site location, and related subject, as applicable.

12.3 Drawing Submittals

12.3.1 The contractor shall submit all drawings, specifications, welding procedures, concrete design mix, substitutions, technical data, and calculations for Purchaser design and fabrication review as required by the contract documents to: For Air Products in America Submittal Coordinator Construction Engineering Department Air Products and Chemicals, Inc. 7201 Hamilton Boulevard Allentown, PA 18195-1501  For Air Products in Europe Purchaser representative for transmission to the respective home office engineer.

12.3.2 All drawing submittals must be accompanied by a transmittal letter. The transmittal letter shall include the information described in paragraph 11.2.2 as well as the desired return date for comments and the name and telephone number of the person to whom any questions can be directed. Turnaround time for this review by Purchaser will vary depending on the scope, but a minimum of seven days shall be allowed for any submittal.

12.3.3 Rebar drawings for all foundations shall be submitted to the Purchaser representative who will transmit to the submittal coordinator. Exceptions must be approved by Purchaser home‑office supervisor.Review or approval of contractor’s drawings, specifications, calculations, technical data, or other submittal information shall not relieve the contractor of the responsibility for the accuracy, workmanship, materials, etc., required by the contract document.

12.4 As-Built Drawings

12.4.1 As-built drawings and records shall be submitted to the Purchaser representative at the completion of work.

12.4.2 A clearly marked-up set of contract drawings, supplemented by the contractor’s sketches as required, is acceptable for as-built drawings. A set of unmarked contract drawings will be provided to the contractor for this purpose if requested. The drawings shall be used to continually document field changes as the work progresses.

12.4.3 All field changes, additions, deletions, substitutions, or corrections of substance shall be included on the as-built drawings. All CCOs and addendum work must be shown on the as-built drawings.

12.4.4 Submittal of complete and accurate as-built drawings (as determined by Purchaser) shall be a condition for the release of final retention moneys to the contractor.

13. FIELD REPORTING

13.1 After moving on-site, the contractor shall submit to the Purchaser representative a weekly report consisting of the following: Manpower on-site by trade and number of hours worked divided into areas based on the breakdown in the weekly schedule, including any subcontractor work forces. Equipment on-site by type and quantity. Description of areas worked and work  accomplished. Documentation of any problems. Daily totals (of construction progress indicators).

13.2 The daily totals to be reported will vary depending on the type and nature of the contract and will be determined by the Purchaser representative at the beginning of the contract work. Typical examples are: Volume of fill in-place. Volume of concrete in-place. Length of ductile iron, cast iron underground pipe in-place. Quantity of carbon steel, stainless steel, copper welded. Tie-ins completed. Length of conduit in-place. Length of cables in-place. Number of terminations completed. Volume of cold box insulated versus total volume required.

13.3 The contractor shall submit daily time sheets, referencing specific CCOs or addendum numbers, for any extra work performed on a construction time and material basis to the Purchaser representative for approval. These daily time sheets must indicate manpower, equipment, and materials for which the contractor requests reimbursement. Failure to submit time sheets daily for Purchaser approval and signature might result in rejection of any claim for reimbursement.

13.4 The contractor and contractor’s subcontractors will be required to meet formally on a weekly basis with the Purchaser representative to discuss the following: Job safety Job progress and scheduling Material delivery Problem areas Status of extra work requests, CCOs, unresolved claims

13.5 The contractor will provide, on a weekly basis, a two-week look ahead schedule. The contractor shall also identify any missing material required to support the work outlined in this schedule.

13.6 Minutes of the weekly meetings will be prepared by the Purchaser representative and distributed to the meeting attendees.

13.7 The contractor shall report all nonconforming conditions to the Purchaser representative (and will do so in writing when requested). Nonconforming conditions are those that cannot be resolved within the scope of existing specifications and will also include design errors. When possible, the affected item will be segregated and labels or markings denoting this condition will be applied. No further work may be performed on the affected item without a written consent from the Purchaser representative.

13.8 When work is being performed in or adjacent to an operating facility, the contractor shall submit at the beginning of each shift a manpower report by name for all personnel on site for that day. This manpower report will be used to verify manpower in the assembly area in case of a site evacuation.

14. MATERIALS AND SUBSTITUTIONS

14.1 All materials provided by the contractor shall be ordered within two weeks after contract award unless specific approval from Purchaser is granted. If required by contract documents, contractor shall furnish unpriced copies of purchase orders with promised delivery dates to the Purchaser representative within three weeks after contract award. The contractor shall immediately notify the Purchaser representative of any long-delivery items that will adversely affect timely execution of the work under this contract.

14.2 The contractor shall furnish all materials, other than those specifically indicated as supplied by Purchaser in the Project Specific Scope of Work or the contract drawings. Included in the contractor’s scope of supply are items or materials specified or covered by descriptive information on the contract drawings.

14.3 All contractor-supplied material shall where appropriate, or as specified in the contract drawings and specifications, be supplied with relevant material certification. The minimum certification requirement for primary pressure‑containing parts, lifting lugs, attachments, and structural steelwork (excluding bolting), shall be either mill certificates (for metallic material originating in the United States) or a 2.3 certificate according to EN 10204. For projects performed within the European Economic Community (EEC), or where specified in the contract documents, such material certificates must comply with the requirements of PED.

14.4 All materials furnished by the contractor shall be new, unused, and in good condition. The use of material for primary pressure‑containing parts, lifting lugs, attachments, or structural steelwork that originates from outside the European Economic Community, United States, Canada, Japan, South Korea, or South Africa requires prior written approval of Air Products when the fluid contained is flammable, toxic, or gas at a pressure greater than 1 bar g (15 psig). Carbon steel flanges produced in The Peoples Republic of China and identified as conforming to ASME B16.5 and ASTM A 105 are not permitted.

14.5 Whenever a material or article is specified on the contract documents through use of a proprietary product name or a particular manufacturer, supplier, model, or catalog number, the contractor shall use only such items unless approval for substitution is requested and obtained from Purchaser. Each substitution request submitted by the contractor shall furnish complete data concerning the material or article proposed for incorporation in the work.

14.6 All substitution requests must be submitted by the contractor in a timely fashion that allows Purchaser ample time for review before purchase and installation.

15. WORKMANSHIP

15.1 The contractor shall employ only labor that has been qualified by training and experience to capably perform the specific activities required to complete this work in the best, most workmanlike manner and in strict conformity with the best standards of practice.

15.2 When in the opinion of the Purchaser representative any of the contractor’s workers are insufficiently qualified to perform their activities, the contractor must either remove these workers from the site and replace them with qualified workers or reassign these workers to other activities. The final determination of the proper course of action in such cases shall be solely that of the Purchaser representative. Purchaser representative may ask the contractor at the contractors cost to have some or all of his workers carry out trade tests (such as welding, scaffolding, or rigging/slinging).

16. SUPERINTENDENTS

16.1 Contractor Superintendent

16.1.1 The contractor’s management shall give personal attention to the execution of this contract and shall ensure there is full-time supervision onsite throughout the entire contract duration. The contractor’s superintendent shall be empowered with full authority to act on all matters related to the contractor’s work or that of contractor’s subcontractors.

16.1.2 The contractor shall employ responsible and competent superintendents who are qualified by experience and training to capably supervise all phases of the work. This experience must include: Commitment to safety procedures and their enforcement. Job planning, forecasting, and scheduling. Use of effective manpower, equipment, and material control techniques. Construction change estimating ability and execution authority. Ability to manage and interface with all subcontractors. Administrative organization and execution of all contract requirements.

16.1.3 The contractor shall include in contractor’s bid a resume of the contractor’s proposed superintendent (including work experience and safety record for past three years). Approval by Purchaser is required before the assignment, transfer, or dismissal of the contractor’s superintendent.

16.1.4 When in the opinion of the Purchaser representative the contractor’s superintendent is insufficiently qualified or fails to meet the requirements of paragraph 16.1.2, the contractor must replace the superintendent with a qualified one. If the Superintendent is unable to execute the project effectively in the opinion of the Purchaser representative, the contractor shall replace him with a more capable person at no cost.

16.2 Purchaser Representative

16.2.1 All material and workmanship is subject to the inspection and approval of the Purchaser representative wherever fabrication, installation, or erection is taking place. This individual will represent Purchaser in all matters relating to the scheduling and execution of the work or the interpretation of contract documents and is empowered with full authority to act on all matters related to the work. The contractor shall fully assist the Purchaser representative with tools, scaffolding, labor, and items necessary for the performance of inspections. The Purchaser representative has the authority to stop work whenever (in the opinion of the Purchaser representative) such stoppage might be necessary to ensure the proper and/or safe execution of the work. Any costs associated with such stoppage(s) shall be borne by the contractor. The contractor may be asked to supply facilities on site for the Purchaser representatives and start‑up personnel. Contractor will be notified in the Project Specific Scope of Work when this is required. Unless modified in the Project Specific Scope of Work, the contractor shall supply accommodations and facilities according to Appendix A.

17. EQUIPMENT AND TOOLS

17.1 The contractor shall provide all tools and equipment necessary to perform the required work described by these specifications or as indicated on the contract documents. All tools and equipment must be maintained in a first-class, safe condition and be of sufficient quantity to ensure the successful completion of the work according to the contract schedule.

17.2 Failure to have proper tooling, which causes delays to other contractors, Purchaser, or its supplier representatives, will result in a backcharge to the contractor for any delay cost incurred.

18. LAYOUT OF WORK AND SITE CONDITIONS

18.1 The contractor is required to visit the site before submittal of contractor’s bid to review the site conditions and layout as well as the scope and specifics of the contract work. The contract will be awarded based on the understanding that the contractor accepts the conditions and circumstances that exist, and no recourse will be granted subsequent to the contract award.

18.2 Within two weeks after moving onto the job site, the contractor shall inspect any previous work performed by others such as foundations, anchor bolts, pipe stub-ups, and valve locations upon which contractor’s subsequent work shall depend. The contractor shall accept, reject, or note exceptions to all such previous work through written notification to the Purchaser representative. Under no circumstances will a contractor be reimbursed for delays or additional costs resulting from contractor’s failure to check existing work or conditions.

18.3 The contractor shall verify the existence of any overhead or underground obstructions. The contractor shall exercise extreme care to prevent damage to existing telephone lines, power lines, water mains, sewer or gas lines, and other aboveground or belowground structures. “Pothole” excavations to verify exact locations of all known underground structures are required before the start of work in any area.

18.4 If the contractor damages existing aboveground or belowground structures, the contractor shall immediately notify the Purchaser representative as well as the utility or third‑party companies having jurisdiction over the damaged facilities. The contractor shall repair or replace any damaged facilities to a condition similar to that which existed before the damage and to the satisfaction of the Purchaser representative. Any and all costs for repair or replacement of damaged work, utilities, materials, equipment, or other properties and structures resulting from failure or negligence on the part of the contractor or contractor’s subcontractors shall be borne by the contractor.

18.5 The import and export of soil, crushed rock, and gravel shall be controlled in the following manner:

18.5.1 For soils, crushed rock, and gravel that is to be brought on-site, test certificates must be supplied showing content and verifying that it is not contaminated.

18.5.2 It is Purchaser preference that soils, crushed rock, and gravel not be removed from its site. If removal is to be performed, prior testing must be performed documenting that it is free from contamination. The Purchaser representative will initiate appropriate transfer documentation. In certain countries the removal of soil is legally controlled and the contractor shall move and manage spoil and material in line with legal requirements including the safe disposal of contaminated soil.

18.6 Areas for construction trailers or site offices, parking, laydown, and storage of materials and equipment will be designated by the Purchaser representative.

18.7 Only vehicles authorized by the Purchaser representative shall be allowed on-site. All others must remain in designated areas, parking areas, or off-site. Contractors’ vehicles must have company identification visible on the outside of the vehicle.

18.8 Only personnel in the employ of Purchaser or its contractors or suppliers shall be allowed on‑site. No other personnel are allowed on-site without the express approval of the Purchaser representative.

19. TEMPORARY FACILITIES

19.1 Temporary Construction Water and Power:  Unless specified in the project-specific scope of work, the contractor shall provide and maintain an adequate supply of water for construction and testing purposes and for domestic consumption, as well as any facilities needed to convey or store the water. The contractor shall provide all construction power. Where a source of water or small power is identified in the project-specific scope of work as being provided by Air Products, the contractor shall be responsible for making connections to the supply. In any event, any power will only be used for site cabins/trailers.

19.2 Temporary Sanitary Facilities:  The contractor shall provide and maintain an adequate number of sanitary, chemical-type, temporary toilets for the use of personnel employed by the contractor, subcontractors, and Purchaser personnel. These facilities shall conform to the requirements of all state, county, and local ordinances and shall be kept clean at all times.

19.3 Temporary Storage and Security

19.3.1 Temporary buildings or trailers required for the storage and protection of Purchaser-supplied materials shall be provided by the contractor. Such temporary structures shall remain the property of the contractor and shall be removed upon completion of the work at contractor’s expense. The contractor shall provide safe means of access to these temporary storage facilities and shall comply with all current National, OSHA (U.S. or U.S. based standards), state, county, and local ordinances or regulations.

19.3.2 The contractor shall provide all site security of contractor work, equipment, and materials, as well as any materials provided by Purchaser to the contractor, until final acceptance by Purchaser.

19.4 Storm Water Runoff:  The contractor shall implement a storm water runoff plan if the site encompasses over a one-acre accumulative area.

20. HOUSEKEEPING

20.1 The contractor shall maintain good housekeeping practices according to 4WCE-600700. The contractor shall provide an adequate number of laborers to maintain cleanliness in the work area. The work area shall be maintained, on a daily basis, in a “broom-swept or debris-free” condition throughout the shift with excess material either neatly stored or removed to storage areas. If the contractor fails to clean up work areas in a timely manner, the Purchaser representative will do so and backcharge the contractor.

20.2 Disposal of all waste (general refuse, construction debris, or special debris) shall be kept separate from each other. The contractor shall be responsible for removing from site and legally disposing of all waste material including packing material at an approved facility. In the United States contractor will be required to use either a Waste Management or Allied Waste (formerly BFI) facility. If either of these facilities is not within a reasonable vicinity of the project, the Purchaser representative shall be contacted for direction. In jurisdictions that require recycle of waste material (such as concrete, asphalt, plastics, steel) the contractor shall meet these local requirements.

20.3 Metal skips or dumpsters with secure lids and covered roll off containers must be used for the collection and storage of all waste material. These shall be emptied every two weeks, when full, or at the discretion of the Purchaser representative and shall be immediately replaced by empty containers. There shall be no liquid allowed in the containers, and there shall be no waste material buried on site. The contractor shall train all personnel on the correct waste disposal procedures.

20.4 The Purchaser representative will advise the contractor when it is considered that the requirements under this section are not being fulfilled. Three days will be allowed for the contractor to take remedial action. If no action is taken by the contractor, the Purchaser retains the right to take such action as is necessary at the contractor’s expense.

21. RECEIVING PURCHASER-SUPPLIED MATERIALS

21.1 The contractor shall submit, along with their proposal, a material receiving plan that addresses how the contractor, Air Products, and purchaser’s customer-supplied material will be handled and managed onsite throughout the course of this portion of the contract. Upon receipt of Purchaser-supplied materials, the contractor shall:

21.1.1 Audit quantities and physical condition of all items.

21.1.2 Accept and acknowledge receipt of materials by signing appropriate transmittal forms or receiving reports and submitting these to the Purchaser representative. All items shall be checked upon receipt for their state of cleanliness, state of paint work, and any loss, damage, or missing materials. If the contractor notices damage to equipment or packing, he shall notify the Purchaser’s representative before offloading for disposition. Any noticeable damage shall be noted on transporter’s weigh bill. The contractor shall complete the purchaser’s “Transportation Loss and Damage Report.”

21.1.3 The contractor shall have a digital camera available to document any shipping damage. Use of this camera for other needs will be limited and will require written authorization from the Purchaser.

21.1.4 The contractor shall provide a written report to the Purchaser representative within 24 hours of receipt of each delivery. Any nonconformance to the Purchaser standards or specifications shall be reported to the Purchaser representative before any remedial action being taken.

21.1.5 Items purged with nitrogen or dry, oil-free air shall be checked upon receipt and at regular intervals thereafter, to ensure that the purge pressure is as shown on the shipping note until the item is finally erected. The contractor shall notify the Purchaser representative before the removal of any nozzle blanks or at any time if the purge pressure is lost or reduced.

21.1.6 When items are supplied with spare valve gaskets and other loose components, the contractor shall store these separately and maintain an inventory for future use.

21.1.7 On receipt of items under vacuum, the contractor shall check the indicated level of vacuum against the shipping note. Contractor will notify the Purchaser representative of any deficiencies found. Loss of vacuum shall be noted on transporter’s weigh bill. The contractor shall notify the Purchaser representative before the removal of any nozzle blanks or at any time that the level of vacuum changes.

21.1.8 On receipt of items containing bags of silica gel, the contractor shall obtain records of the number of bags and check that the bags are in place. They shall only remove them just before final erection, and a counting-out system shall be maintained in writing to ensure that all of the bags are removed.

21.1.9 Any caps, blind flanges, bags, wrapping, or other protection supplied with materials and equipment shall be maintained in place by the contractor until immediately before final erection. All items shall be inspected immediately before final erection. Any equipment found to have been soiled during erection or storage shall be recleaned at the contractor’s expense.

21.1.10 The contractor shall provide a clean, dry, and secure store for free-issue materials that is to be properly laid out with racks, bins, or other equipment necessary to store and retrieve material in an orderly fashion. If a store is established offsite, the transport insurance and logistics costs for returning the materials to site, and its secure site storage and the handling shall be included by the contractor.

21.1.11 The contractor is responsible for supplying suitable cribbage, timbers, or pallets as necessary to properly store material off the ground.

21.1.12 The contractor shall provide qualified personnel to operate a complete materials receiving and issuing control procedure. Comprehensive records shall be maintained, and compared against Purchaser and contractor material lists to enable an accurate shortage list to be prepared at any given time. The Purchaser material coding system shall be used to control the movement of materials. The contractor shall be required to issue Goods Received Notes (GRNs) or receiving reports acceptable to the Purchaser expediting group.

21.1.13 Where specified, the contractor shall receive, unload, and store items of instrument and electrical equipment. The contractor shall prepare receiving reports for this equipment as described above. For items for which the contractor is not responsible for erection, the contractor shall prepare documentation to record the handover of this material to others.

21.1.14 Relief valves will be received into the contractor’s store and may be used for piping fit-up. Contractor is cautioned not to break the calibration seal wires. If the seal wire is broken the relief valve will require recalibration, which will be to the contractors account. Contractor may elect to provide, at their cost, temporary spool pieces to allow the installation of piping without installation of the relief valves.

21.1.15 When construction work is complete, surplus materials will be dispatched from the site. The contractor shall be responsible for packing these materials, preparing a detailed packing list, “Return of Goods Authorizations,” and providing the relevant material certificates. The contractor is to note that it is essential that pipe markings are copied onto each cut length of pipe. The contractor shall be responsible for loading surplus materials onto transport provided by the Purchaser and for the disposal of all scrap metal, packing, shipping saddles, drums, and other material not to be reused by the Purchaser.

21.1.16 Containers, when used, may be either end-loading or open-topped. The contractor’s price shall include for unloading either type.

21.2 The contractor must obtain approval from the Purchaser representative for the contractor’s off-loading and erection procedures for all major equipment provided by Purchaser. The contractor must submit this procedure at least three weeks in advance of the lift to allow ample time for review and approval according to 4WCE-600500.

21.3 Upon acceptance of the materials, the contractor shall assume full responsibility for protecting all items from loss or damage and maintaining them in a satisfactory condition until acceptance of the system, area, or plant by the Purchaser representative.

22. PROTECTION OF MATERIALS AND WORK

22.1 The contractor shall administer a program according to sound industrial practice to protect and preserve all materials, supplies, equipment, and all work that has been performed (such as lubrication, purging, barriers, space heaters, painting) by either the contractor, contractor subcontractors, Purchaser, or other previous and present contractors. This includes, but is not limited to, damage resulting from weld slag. All instruments, electrical wire, cable tray, tubing, thin‑wall piping (Schedule 5 or 10), and other items that might be damaged, shall be covered with a fire-retardant material or protected by an adequate spark catcher to contain sparks and slag. Any arcs or weld slag damage found on tubing, electrical wiring, instruments, piping, or other equipment shall be replaced or repaired by the contractor according to Purchaser procedures and specifications.

22.2 Equipment and materials shall be adequately preserved and maintained both during storage and after installation/erection. The contractor will develop a maintenance log which will list all required activities and frequency of performance. The contractor is fully responsible for providing appropriate preservation in the form of purging (including the supply of purge gases), capping, and other methods. Use of preserving oils might be required on some equipment or material, but generally, care should be taken since oils are a hazard in oxygen systems. Generally, preservation by purging with dry, oil-free air is preferred.

22.3 Purchaser-provided material shall be stored and protected as follows.

22.3.1 Small and specialty items shall be stored indoors. These items include, but are not limited to: Valves Instruments Filters Strainers Gaskets Rupture discs Tubing Instrument fittings All material identified “Cleaned for Oxygen Service” (Material must be kept in factory packaging until installation.)

22.3.2 Items stored outdoors shall be placed on pallets or timbers to prevent them from laying in mud or water, hidden by weeds, trash, construction equipment, and/or other equipment and materials. All open or exposed ends of pipe and/or equipment shall be covered to prevent exposure to foreign matter and to prevent oxidation from occurring. Material must be protected from rain, snow, and wet conditions. More specific instructions on storage and handling of special materials might be included with the Site/Project specific documentation included in the contract. Replacement cost for any and all lost or damaged Purchaser-provided material resulting from improper storage will be the responsibility of the contractor. When requested by the Purchaser representative, the contractor shall repair, clean, replace, or restore such items to the condition required by the appropriate specification.

22.4 All methods and procedures for repair, cleaning, or restoring damaged materials and equipment shall be submitted in writing for approval by the Purchaser representative. Purchaser reserves the right to make these repairs or to have its supplier’s representative make these repairs as appropriate, and to backcharge the contractor for any costs thereby incurred.

22.5 Any material that must be replaced by Purchaser because of damage or misplacement by the contractor will be billed to the contractor at cost, including freight, plus a handling fee of $100. If the damaged or lost material results in a construction-schedule extension, additional costs might be billed to the contractor by Purchaser.

22.6 The contractor shall have a system in place that addresses the removal of items such as materials and tools from the jobsite. No materials, hazardous or nonhazardous, provided by Purchaser shall leave the jobsite without the written authorization of the Purchaser representative. Removal of hazardous material(s) without the written permission of the Purchaser representative shall be cause to permanently bar those involved from the site as well as initiate any appropriate legal action against the individual(s) and/or contractor. Material leaving the site shall leave through the designated gate and it will be necessary for these items to be identified. The Purchaser representative and security guards, when employed, are authorized to inspect all vehicles and parcels.

23. TESTING

23.1 The Purchaser representative shall be notified 48 hours before the performance of any tests or inspections.

23.2 All tests and inspections required by the contract documents shall be made by a properly qualified person or testing laboratory and shall be performed in the presence of the Purchaser representative. Reports shall be furnished to document the results of these tests and shall state that they were made according to the provisions specified in the contract documents. When a test result indicates that the specified minimum result was not achieved, the contractor shall immediately notify the Air Products representative, in writing, of this nonconforming product. The contractor shall provide a copy of the necessary documents to the Air Products representative, along with a recommended remediation for Air Products’ consideration. Measuring, inspection, and testing equipment shall be calibrated as required by the contract documents and, when applicable, industry standards. When no such standards exist, the basis used for calibration shall be identified. A documented procedure is required for all equipment that is to be calibrated. All calibrated equipment shall be in good condition and shall be labeled or tagged indicating the current status and identifying who performed the calibration and the date. Contractor shall provide copies of all calibration certificates as part of their QA/QC documentation. When applicable any environmental limitations shall be determined and strictly followed. Unauthorized adjustment of calibrated equipment is not permitted. If it is found that the equipment was out of calibration during its use on the project, the Purchaser representative must be notified immediately since this will be considered a nonconforming condition.

23.3 All test reports must be co-signed by the contractor and the Purchaser representative.

23.4 The test or operation of any piping, equipment, or facilities without the prior knowledge and concurrence of Purchaser will transfer to the contractor complete liability for any direct or consequential damages, including equipment warrantees if voided by the manufacturer because of an unauthorized test.

23.5 Testing of Pipework

23.5.1 The contractor shall be responsible for the testing of all pipework by hydrostatic or pneumatic testing as stipulated by the Purchaser in the pressure test procedure and according to Purchaser specifications. For cryogenic plants, hydrostatic testing of piping shall only be allowed for lines in water, steam, or condensate service. For all process piping, only pneumatic testing shall be acceptable.

23.5.2 The contractor shall be responsible for preparing detailed test packages for submittal to the purchaser for review and approval before testing. Specific requirements will be as specified in the appropriate contract document (for example, 4WPI-EW44001).

23.5.3 The contractor shall supply all necessary spades, blinds, manifolds, valves, gaskets, and bolts in order to perform this work together with certified gauges, test relief valves, and pumps or compressors. The contractor shall also provide any test media required (such as oil-free compressed air, nitrogen, or helium) to perform the specified tests.

Note: Applies to Mechanical contracts only.

23.5.4 The contractor shall be responsible for organizing, and any costs associated with, third-party inspections or witness testing. Scheduling such inspection to meet the construction program shall be the contractor’s responsibility.

23.5.5 The contractor shall be responsible for removing nonreturn valve internals and control valves as necessary, and for providing temporary supports (if required) before pressure testing. Contractor is also responsible for drain down and reinstating the line after the completion of pressure testing.

23.5.6 Drying of lines and any purge reinstatement shall be to the contractor’s cost.

23.6 Pre-commissioning of Equipment (General)

23.6.1 Immediately upon completion of each piece of equipment or system and after completion of a full punch-out with completion of all remedial actions by the contractor, the contractor shall notify the Purchaser representative that the particular items have been given all necessary preliminary checks and are ready for test operation. The Purchaser representative will inspect the equipment or system and, when satisfied, will issue a schedule and instructions for test operation. The contractor shall not put into operation any equipment furnished by the purchaser without the prior approval of the Purchaser representative. Failure to adequately punch out systems by the contractor which results in additional cost to the Purchaser shall be backcharged by the Purchaser to the contractor.

23.6.2 The contractor will be required to provide labor to assist the Purchaser specialists during commissioning.

23.7 Engineering Audit

23.7.1 After completion of construction, an engineering audit will be performed by the Purchaser in conjunction with the contractor and a punch list will be established. This work will need to be executed to maintain the overall schedule.

23.7.2 Where rectification of punch list items are the responsibility of the contractor, the contractor shall provide skilled labor and the necessary material and equipment to rectify these punch list points at their cost and to meet the required schedule.

23.7.3 The contractor shall provide skilled labor for rectification of other punch list items that are not the contractor’s responsibility (such as specialist or operational readiness inspection punch lists) on an agreed basis (for example, lump sum, day works, schedule of rates).

24. ACCEPTANCE OF WORK

24.1 All work must be accepted in writing by the Purchaser representative to handover responsibility from the contractor to Purchaser as defined in this specification.

24.2 Areas of work may be conditionally accepted by Purchaser before final completion of the entire job to allow Purchaser personnel to operate and test equipment in that area. If the contractor anticipates any trade disputes from this partial acceptance procedure, this must be detailed in the contractor’s proposal.

24.3 All accepted areas shall be complete and ready for start-up operations.

24.4 Acceptance by Purchaser and/or the owner of any or all items shall not be construed as relieving the contractor of responsibility for performance, workmanship, materials, or any other stipulations required by the contract.

25. CLEARING THE SITE

25.1 Upon completion of the works, the contractor shall remove all temporary facilities erected by them and their subcontractors, all temporary roads, fences, and footpaths installed by them and their subcontractors, all construction equipment, surplus materials, and supplies belonging to the contractor and their subcontractors, and shall leave the site in perfect order, clean and ready for use, to the satisfaction of the Purchaser representative.

25.2 The contractor shall make a reasonable allowance for any work to allow the removal of surplus equipment or materials belonging to the purchaser (such as cutting up saddles, structures, and consolidating surplus piping material).

25.3 The contractor shall be responsible for cleaning and repainting where necessary, surfaces contaminated by weld splatter or grinding dust (for example, the roofs and sides of cold boxes and column cans, piping protective coatings). If more than one contractor has contributed to this, a reasonable split of responsibility shall be agreed upon with the Purchaser representative.

Appendix A Purchaser’s Site Establishment Requirements

A1. This appendix defines the requirements for contractors asked to provide site establishment for the purchaser or other parties at site. Unless specified in the project detailed scope of work, it shall be considered as a minimum requirement. It details the extent of the expected establishment, the services to be provided by the contractor, and the equipment that shall be provided. The contractor shall include these costs in his preliminaries based on the key dates and not on a monthly rental basis.

A2. Extent

A2.1 The following shall be provided: For the Purchaser site manager/representative, a separate office of suitable size. Four double offices, each for two construction engineers (total eight). Conference room facilities. Toilet, washing, and light cooking facilities included in the office accommodation.

A3. Equipment

A3.1 All accommodation shall include furniture, tables, chairs (including conference room chairs).

A3.2 Storage cabinets for correspondence and drawings.

A3.3 Storage cabinet for safety supplies.

A3.4 Drawing rack file.

A3.5 Plan review table.

A3.6 Hat and coat rack.

A3.7 Firefighting equipment.

A3.8 A white board in each of the offices.

A3.9 Microwave oven, electrical kettle, and refrigerator.

A3.10 Air conditioning, where the normal practice of the country.

A3.11 Heating

A4. Options

A4.1 The contractor shall provide an option price for the provision of a common photocopier and telefax machine installed with the Purchaser office complex. The contractor shall also provide a separate option for the supply of telephone instruments.

A5. Standards

A5.1 The site establishment shall be supplied to meet all the national and local regulation for the place of installation.

A5.2 If no statutory requirements exist, fire rating/resistance, means of escape, and electrical installations shall conform to an internationally recognized standard or code of practice to be agreed with the Purchaser.

A5.3 All cabins, equipment, and materials shall be in good order, free from damage, and in an “as new” condition.

A5.4 All accommodations shall be lockable and secure from pilfering.

A5.5 If double stacking of cabins is necessary due to limited space, this shall only be done with the approval of the Purchaser representative. Safe and secure means of access shall be provided. This shall be nonslip and free from trip or snagging hazards.

A5.6 If cabins are off the ground, suitable netting or equivalent shall be provided to prevent debris and rubbish from accumulating or animals entering underneath the accommodation.

A6. Services

A6.1 The contractor shall be responsible for the off-loading, positioning, installation, and hooking-up of electricity, sewage, water, and telephone facilities.

A6.2 All such installation work shall be performed to an agreed, acceptable, national standard or code of practice.

A6.3 The contractor shall maintain the accommodation and equipment in good working order and replace immediately anything that, in the Purchaser representative’s opinion, is substandard or broken.

A6.4 The contractor shall include for the costs involved in the dismantling and demobilization of the accommodation at the end of the project, including removal of redundant cables and underground pipework and the reinstatement of the area back to the condition in which it was originally received by the contractor.

A6.5 The contractor shall provide for full janitorial services on a biweekly basis.

Leave a Reply

Your email address will not be published. Required fields are marked *